Notice to Contractor in Georgia
If you supplied labor, materials, or equipment on a private Georgia construction project and you don't have a direct contract with the general contractor, a Notice to Contractor may be one of the first things you need to get right. When the statute requires it, it is a required step for claimants in your position O.C.G.A. § 44-14-361.5. This guide covers who must send a Notice to Contractor in Georgia, the deadline that controls it, what it has to say, and how the "no Notice of Commencement" exception works.
What a Notice to Contractor Is
A Notice to Contractor is a statutory letter required under O.C.G.A. § 44-14-361.5. It tells the owner and the general contractor that you're on the job supplying labor, services, or materials, even though neither of them hired you directly. It is a separate document from a Claim of Lien. It puts the owner and the contractor on written notice of who you are, who you're furnishing for, and what you're furnishing.
Who Actually Has to Send One
The notice requirement is narrow. Under Georgia law, a Notice to Contractor is required only from claimants who lack privity of contract with the prime contractor: sub-subcontractors, and suppliers who sell to a subcontractor rather than to the prime contractor directly O.C.G.A. § 44-14-361.5.
- If your contract is directly with the prime contractor, you have privity with the contractor and this notice requirement is not aimed at you.
- If your contract is with a subcontractor — you're a sub-subcontractor, or you supply materials to a subcontractor — the notice requirement is built for you. (A supplier to another supplier has no lien rights under Georgia law O.C.G.A. § 44-14-361.)
There's a second condition that matters just as much: the requirement only applies on projects where a Notice of Commencement was filed. We cover the exception for projects without one below.
The Deadline: the Later-of-Two Rule
Georgia sets the deadline as the later of two dates under O.C.G.A. § 44-14-361.5, not the earlier:
- 30 days from the date the Notice of Commencement was filed, or
- 30 days from the date you first delivered labor, services, or materials to the project
whichever comes later. In practice: if the Notice of Commencement was already on file before you started, your 30 days run from your first delivery of labor, services, or materials. If the Notice of Commencement was filed after you'd already been working for weeks, your 30 days run from the date it was filed, not from your first day on site. Getting the "later of" comparison backwards is an easy mistake to make, and it's the kind of fact-specific calculation an eligibility review checks.
What the Notice Must Say
The statute lists what a Notice to Contractor must contain O.C.G.A. § 44-14-361.5:
- Your name, address, and phone number
- The name of the person or company you're actually furnishing labor, services, or materials for (usually the subcontractor who hired you)
- The project's name and location
- A description of what you're furnishing, along with the contract price or amount you're claiming
This isn't a form to freehand from a template you found online. Get each item right the first time; whether a particular notice is sufficient is a question for the attorney review.
Serve Both Recipients, Not Just One
This detail is easy to miss: the Notice to Contractor has to go to both the owner (or the owner's agent) and the general contractor, not one or the other, and it has to go to the addresses listed in the recorded Notice of Commencement O.C.G.A. § 44-14-361.5. Send it by registered or certified mail, or by statutory overnight delivery, and keep your proof of mailing and delivery. The statute calls for delivery to both; sending it to only one is not what the statute requires.
No Notice of Commencement: When the Notice to Contractor Requirement Doesn't Apply
Here's the exception that surprises people in the other direction. O.C.G.A. § 44-14-361.5 only applies at all when a Notice of Commencement was filed for the project. If the owner and general contractor never filed one, the statute doesn't apply to you, and failing to send a Notice to Contractor does not, by itself, forfeit your lien rights on that project.
That's good news, but it isn't permission to stop paying attention. You still need to confirm, in fact, whether a Notice of Commencement was filed rather than assume it wasn't. A filed Notice of Commencement is a recorded document; checking for one is part of what an eligibility review does before anything gets filed.
Notice to Contractor vs. Preliminary Notice of Lien Rights
These two get confused constantly. A Notice to Contractor is mandatory for claimants without privity, on Notice-of-Commencement projects, within the later-of-30-days window above. A Preliminary Notice of Lien Rights is a different, optional filing under O.C.G.A. § 44-14-361.3 that a claimant may elect to file with the superior court clerk within 30 days after first delivery. It isn't a prerequisite to lien rights generally. Whether or not you file one, check separately whether a Notice to Contractor is required from you.
Why This Matters More Than It Looks Like It Does
When a Notice to Contractor is legally required O.C.G.A. § 44-14-361.5, what a missed notice means for your lien rights depends on your tier and the project facts — which is exactly what an attorney review is for. Because the deadline is short, easy to miscalculate, and depends on paperwork you may never have personally seen, this is a notice worth getting reviewed rather than guessed at. Georgia Lien Desk reviews eligibility first and declines what we can't ethically file; contested litigation and bond claims are referred out or handled under a separate engagement. Our current scope is private commercial Georgia projects with claims roughly $5,000 to $100,000, for contractors, first-tier subcontractors, suppliers (including suppliers to subcontractors), and equipment rental companies. Sub-subcontractors are not in our current scope; if you are one, ask us by email at info@georgialiendesk.com before purchasing a review.
Frequently Asked Questions
What is a Notice to Contractor in Georgia?
It's a statutory notice required from claimants who don't have a direct contract with the general contractor, sub-subcontractors and suppliers to subcontractors, telling the owner and general contractor that they're furnishing labor or materials on the project O.C.G.A. § 44-14-361.5. It is required only on projects where a Notice of Commencement was filed.
Who has to send a Notice to Contractor?
Only claimants without privity of contract with the prime contractor, and only on projects where a Notice of Commencement was filed O.C.G.A. § 44-14-361.5. If your contract is directly with the prime contractor, this requirement is not aimed at you.
What is the deadline to send a Notice to Contractor in Georgia?
Within 30 days of the later of (a) the Notice of Commencement being filed, or (b) your first delivery of labor, services, or materials to the project O.C.G.A. § 44-14-361.5. Your actual deadline depends on both dates, so it has to be calculated, not assumed.
What if there's no Notice of Commencement on the project?
Then the Notice to Contractor requirement doesn't apply, and not sending a Notice to Contractor does not, by itself, forfeit your lien rights O.C.G.A. § 44-14-361.5. You should still confirm, not assume, that no Notice of Commencement was actually filed.
Is a Notice to Contractor the same as a Preliminary Notice of Lien Rights?
No. A Preliminary Notice of Lien Rights is an optional filing at the claimant's election O.C.G.A. § 44-14-361.3. A Notice to Contractor is required from claimants who lack privity with the prime contractor on projects where a Notice of Commencement was filed O.C.G.A. § 44-14-361.5. Check each one separately.
Who prepares my Notice to Contractor at Georgia Lien Desk?
At Georgia Lien Desk, every filing is prepared under the supervision of and reviewed by a licensed Georgia attorney.
For claimants within our current scope, Georgia Lien Desk's Notice to Contractor package covers attorney review, preparation, and delivery of your notice to both required recipients for a flat fee. Not sure whether you're required to send one, or when your clock actually started? Run your dates through the lien deadline calculator, and see our guides on Georgia mechanics lien deadlines and how to file a mechanics lien in Georgia for the steps that come after notice.