How to File a Mechanics Lien in Georgia
Filing a mechanics lien in Georgia is a real legal filing, not a form you fill in and forget. Leave off the content Georgia's statute requires on the face of the lien — including the mandatory warning language — and the lien can be invalid even if you filed it on time O.C.G.A. § 44-14-361.1. Here is the process to file a mechanics lien in Georgia, step by step, plus where do-it-yourself filings can go wrong.
Georgia Lien Desk reviews your eligibility before we prepare anything. Our current scope is private commercial Georgia projects with claims roughly $5,000 to $100,000, for contractors, first-tier subcontractors, suppliers (including suppliers to subcontractors), and equipment rental companies, and we decline what we can't ethically file. Contested litigation and bond claims are referred out or handled under a separate engagement.
These steps are a general overview, not a complete checklist of everything Georgia's lien statutes require.
The seven steps to file a mechanics lien in Georgia
1. Confirm your eligibility and tier
Georgia gives lien rights to contractors, subcontractors, sub-subcontractors, and material suppliers — but only suppliers to the owner, a contractor, or a subcontractor. A supplier to another supplier has no lien rights under Georgia law O.C.G.A. § 44-14-361. Laborers, registered architects, engineers, land surveyors, foresters, registered interior designers, machinists, and equipment rental companies furnishing for the improvement of real estate are covered too. Your tier, together with whether a Notice of Commencement was filed, also determines whether a Notice to Contractor was required from you. Get this wrong at the start and everything that follows is wasted effort.
2. Confirm your deadlines
Your Claim of Lien has to be filed within 90 days after your completion of work or last furnishing of materials or machinery O.C.G.A. § 44-14-361.1. If you don't have a direct contract with the prime contractor and a Notice of Commencement was filed for the project, you also needed to send a Notice to Contractor within 30 days of the later of the Notice of Commencement's filing or your first furnishing O.C.G.A. § 44-14-361.5. Both clocks run from facts, not from your invoice or your patience running out. Our full deadline guide lays out the main deadlines in one table; run your specific dates through the deadline calculator before you draft anything.
3. Identify the owner and the property
The owner matters twice. The lien is a claim against the owner's property, and the owner is the one who must be sent a copy within 2 business days after filing O.C.G.A. § 44-14-361.1. The party who hired you is not always the owner, so confirm who owns the property, and exactly which property the project sits on, before anything is drafted. Getting the owner and the property right is part of the attorney review.
4. Draft your lien with the mandatory legend
Georgia's claim of lien statute requires specific statutory content, and a 12-point bold warning: "This claim of lien expires and is void 395 days from the date of filing of the claim of lien if no notice of commencement of lien action is filed in that time period," plus notice of the owner's right to contest O.C.G.A. § 44-14-367. Leave any of that off and the lien can be invalid regardless of whether you filed on time. The lien amount is the amount due under your contract, subcontract, or purchase order, plus interest. Attorney fees are not part of the lien amount O.C.G.A. § 44-14-361.
5. Record it with the superior court clerk
You file the completed lien with the clerk of superior court in the county where the property is located. The recording fee is a flat $25 per instrument O.C.G.A. § 15-6-77. Some counties accept e-filing through the GSCCCA portal (a 3.5% card fee or $0.50 ACH fee applies there), but e-filing is county-participation-based, not mandatory statewide — check whether your county's clerk requires or even accepts it before you assume you can file online.
6. Serve a copy within 2 business days
Filing isn't the finish line. Send a true and accurate copy of the lien to the owner no later than 2 business days after filing, by registered or certified mail or statutory overnight delivery O.C.G.A. § 44-14-361.1. Can't find the owner's address? Send it to the contractor as the owner's agent instead. If the owner is a business entity on file with the Georgia Secretary of State, sending the copy to the entity's or its registered agent's address satisfies the rule. If a Notice of Commencement was filed, send a copy to the contractor at that notice's address too.
7. Calendar your 365-day enforcement window
Your lien doesn't enforce itself. You have 365 days from the filing date to commence a lien action, and a Notice of Commencement of Lien Action must then be filed with the same clerk within 30 days after you commence that action O.C.G.A. § 44-14-361.1. Both steps are required, and the lien itself must warn that it expires and is void 395 days from filing if no Notice of Commencement of Lien Action has been filed by then O.C.G.A. § 44-14-367. Calendar the 365-day date the day you file, and calendar the 30-day notice the day the lien action is commenced. A Notice of Contest filed by the owner or contractor can shorten this window — treat 60 days from receipt as the working deadline, and remember it never extends the original 365 days O.C.G.A. § 44-14-368.
Where DIY lien filing goes wrong
- Assuming the party that hired you is the property owner without checking
- Filing against the wrong tier — a supplier-to-a-supplier trying to file when the statute gives them no lien rights at all O.C.G.A. § 44-14-361
- Counting the 90 days from the wrong date instead of your completion of work or last furnishing of materials or machinery O.C.G.A. § 44-14-361.1
- Leaving off the mandatory 12-point bold warning language, which can invalidate an otherwise timely lien O.C.G.A. § 44-14-367
- Serving notice late, or serving only the owner when a filed Notice of Commencement means the contractor needed a copy too O.C.G.A. § 44-14-361.1
- Including attorney fees in the lien amount — they are not part of it O.C.G.A. § 44-14-361
- Assuming a Claim of Lien filing alone stops a signed lien waiver from converting after 90 days — it hasn't, since January 1, 2021 O.C.G.A. § 44-14-366
- Assuming every Georgia county accepts e-filing — it's county-by-county, not statewide
What attorney review adds before you file
Filling in a lien form is the easy part. The legal questions come first: whether you have lien rights on this project, whether your deadline is still open, and whether the filing carries the content Georgia's statute requires. At Georgia Lien Desk, every filing is prepared under the supervision of and reviewed by a licensed Georgia attorney. Our Lien-Rights Eligibility Review is $195, credited toward a Notice to Contractor, Affidavit of Nonpayment, or Claim of Lien package purchased within 7 days after we deliver the review. Our Claim of Lien package is $695 plus costs (the recording fee, any e-filing processing fee, and mailing, passed through at cost) — a flat fee, stated before you pay, for a Georgia attorney's review of your eligibility, your deadline, and the required lien content before anything is filed.
Frequently asked questions
How do I file a mechanics lien in Georgia?
Where do I file a Georgia mechanics lien?
How much does it cost to file a lien in Georgia?
Do I have to e-file my Georgia lien?
Can an unlicensed contractor file a lien in Georgia?
Who prepares my Claim of Lien at Georgia Lien Desk?
Ready to file? See our Claim of Lien package ($695 plus costs). Still not sure you have a claim? Start with a Lien-Rights Eligibility Review ($195) by emailing info@georgialiendesk.com. You can also run your dates through the lien deadline calculator for a general estimate, or read the full deadline guide and Notice to Contractor guide before you draft anything.