Georgia Mechanics Lien Deadlines: The Master Timeline

If you're owed money on a Georgia construction project, you're not working against one deadline. You're working against several, and they start running on different days. Miss the wrong one and you can lose lien rights you never realized were expiring. This page lays out the main Georgia mechanics lien deadlines for claimants in one table, with the statute for each, then explains each one in plain English. It is a general overview, not a complete list of every deadline that can apply to your project.

Georgia Lien Desk reviews eligibility first and declines what we can't ethically file. Our current scope is private commercial Georgia projects with claims roughly $5,000 to $100,000, for contractors, first-tier subcontractors, suppliers (including suppliers to subcontractors), and equipment rental companies. Contested litigation and bond claims are referred out or handled under a separate engagement.

Deadlines are unforgiving. The dates on this page are general statutory rules — your deadline depends on facts like your last day of work, your tier, and recorded notices. If money is unpaid, start your review now, not the week the deadline lands.

The master deadline table

Event / TriggerDeadlineStatute
Preliminary Notice of Lien Rights (optional)Within 30 days after your first delivery of labor or materialsO.C.G.A. § 44-14-361.3
Notice to Contractor (only if you lack privity with the prime contractor and a Notice of Commencement was filed)Within 30 days after the later of the Notice of Commencement's filing or your first furnishingO.C.G.A. § 44-14-361.5
Claim of LienWithin 90 days after your completion of work or last furnishing of materials or machineryO.C.G.A. § 44-14-361.1
Serving a copy of the Claim of LienNo later than 2 business days after filingO.C.G.A. § 44-14-361.1
Affidavit of Nonpayment (if you signed a lien waiver and haven't been paid)Before the 90-day period after you signed the waiver runs outO.C.G.A. § 44-14-366
Serving a copy of the Affidavit of NonpaymentWithin 7 days of filingO.C.G.A. § 44-14-366
Lien action (lawsuit to enforce your lien)Within 365 days from the date your Claim of Lien was filed for recordO.C.G.A. § 44-14-361.1
Notice of Commencement of Lien Action (after you sue)Within 30 days after commencing the lien actionO.C.G.A. § 44-14-361.1
Responding to a Notice of Contest filed by the owner or contractorTreat 60 days from receipt as your working deadline to sue; by law the lien is extinguished 90 days after the Notice of Contest is filed unless a Notice of Commencement of Lien Action is on file by then. A Notice of Contest never extends the original 365-day deadlineO.C.G.A. § 44-14-368
Expiration warning printed on every lienYour lien expires and is void 395 days from the date it was filed if no Notice of Commencement of Lien Action has been filed by thenO.C.G.A. § 44-14-367

Each deadline, explained

Preliminary Notice of Lien Rights — optional, 30 days

Georgia law lets you file a Preliminary Notice of Lien Rights within 30 days after you first deliver labor or materials to a project O.C.G.A. § 44-14-361.3. It's optional — filing it is not a prerequisite to lien rights generally. If you elect to file one, it is filed, for a small clerk's fee, with the clerk of superior court in the county where the property sits.

Notice to Contractor — 30 days, but only if it applies to you

A Notice to Contractor is required only if you lack a direct contract with the prime contractor (for example, a sub-subcontractor or a supplier to a subcontractor) and only on projects where a Notice of Commencement was filed. If both apply, send the notice within 30 days of whichever came later: the Notice of Commencement's filing or your first furnishing O.C.G.A. § 44-14-361.5. It goes to both the owner and the contractor, at the addresses on the recorded Notice of Commencement, by registered or certified mail or statutory overnight delivery. No Notice of Commencement on file means this requirement doesn't apply, and skipping it does not, by itself, cost you your lien rights on that project.

Claim of Lien — 90 days after completion of work or last furnishing

This is the filing most people mean when they say "file a lien." The general rule: you have 90 days after your completion of work or last furnishing of materials or machinery to file a Claim of Lien with the clerk of superior court in the county where the property is located O.C.G.A. § 44-14-361.1. Pinning down that date matters enough that we cover it in its own guide, Last Date of Furnishing in Georgia.

Serving the lien — 2 business days

Filing with the clerk isn't the end of the job. You also have to send a true and accurate copy to the owner no later than 2 business days after filing, by registered or certified mail or statutory overnight delivery O.C.G.A. § 44-14-361.1. If you can't find the owner's address, you can serve the contractor instead, as the owner's agent; if the owner is a business entity registered with the Georgia Secretary of State, sending the copy to the entity's or its registered agent's address on file satisfies the rule. If a Notice of Commencement was filed for the project, you also have to send a copy to the contractor at the address on that notice.

Affidavit of Nonpayment — before the 90-day waiver clock runs out

If you ever signed a lien waiver (interim or final), Georgia law treats it as conclusively effective on the earliest of three events: you actually receive payment, payment is acknowledged in writing, or 90 days pass from the date you signed it O.C.G.A. § 44-14-366. That third trigger is the trap — sign and simply wait, and it becomes conclusively effective once the 90 days have run, whether or not you were paid. Only a timely Affidavit of Nonpayment, filed in the property's county before the 90 days expire, stops that conversion; a copy must then be sent within 7 days of filing. The safe practice is to send it to the owner and, where a Notice of Commencement was filed, to the contractor as well. Filing a Claim of Lien does not stop this clock — that rule changed January 1, 2021; some older articles online still describe the pre-2021 60-day window.

Lien action and Notice of Commencement of Lien Action — 365 days to sue, then 30 days after you sue

Filing your Claim of Lien doesn't make it enforceable forever. You have 365 days from the date the lien was filed for record to commence a lien action (a lawsuit) O.C.G.A. § 44-14-361.1. Once you file that suit, a Notice of Commencement of Lien Action must be filed within 30 days after you commence it, with the clerk of the superior court in the county where the lien was filed. Both steps are required, and the lien itself must warn that it expires and is void 395 days from filing if no Notice of Commencement of Lien Action has been filed by then O.C.G.A. § 44-14-367.

Notice of Contest — the clock an owner can force on you

An owner, contractor, or their attorney can file a Notice of Contest with the superior court clerk, and a copy has to be sent to you within 7 days O.C.G.A. § 44-14-368. Once that happens, your year-long enforcement window collapses: by law, the lien is extinguished 90 days after the Notice of Contest is filed unless a Notice of Commencement of Lien Action is filed in that window, and the notice itself tells you to commence a lien action within 60 days of receiving it. In practice, treat 60 days from the day you receive a Notice of Contest as your working deadline to sue — and remember a Notice of Contest never extends your original 365 days. Whichever deadline comes first controls.

Frequently asked questions

What is the deadline to file a mechanics lien in Georgia?
In general, you must file your Claim of Lien within 90 days after your completion of work or last furnishing of materials or machinery O.C.G.A. § 44-14-361.1. That's a general statutory rule — your actual deadline depends on your last-furnishing date and other facts an attorney should confirm.
What happens if I miss the 90-day deadline to file my lien?
The general statutory rule is that a Claim of Lien must be filed within 90 days after your completion of work or last furnishing of materials or machinery O.C.G.A. § 44-14-361.1. If that date has passed or is close, don't assume anything about what remedies remain — that depends on facts an attorney must evaluate. That's why an eligibility review should happen the moment payment stalls, not after the deadline looks close.
Does filing a Claim of Lien stop the 90-day lien waiver clock?
No. Since a January 1, 2021 change in the law, only a timely Affidavit of Nonpayment stops a signed lien waiver from converting against you after 90 days O.C.G.A. § 44-14-366. Filing a Claim of Lien alone no longer works, even though it did before that date.
How long is a Georgia mechanics lien effective once it's filed?
A Claim of Lien must warn that it expires and is void 395 days from the filing date if no Notice of Commencement of Lien Action has been filed by then O.C.G.A. § 44-14-367. Don't treat 395 days as your deadline: the lien action must be commenced within 365 days of filing, and the Notice of Commencement of Lien Action is due within 30 days after you commence it O.C.G.A. § 44-14-361.1.
What is a Notice of Contest and how does it change my deadline?
It's a filing an owner or contractor can use to force the issue. Once a Notice of Contest is filed, the lien is extinguished by law 90 days after that filing unless a Notice of Commencement of Lien Action is filed in that period, and the notice tells you to sue within 60 days of receiving it O.C.G.A. § 44-14-368. Treat 60 days from receipt as your working deadline; a Notice of Contest never extends the original 365-day deadline.
Do I need to send notice after I record my lien?
Yes. A true and accurate copy of the Claim of Lien must be sent to the owner no later than 2 business days after filing, and to the contractor as well if a Notice of Commencement was filed for the project O.C.G.A. § 44-14-361.1.
Where do I file a Georgia mechanics lien?
With the clerk of superior court in the county where the property is located O.C.G.A. § 44-14-361.1. Our step-by-step filing guide walks through recording and service in order.

Tracking this many clocks on top of running your business is how legitimate lien rights get lost. For a general estimate of your dates, run them through the lien deadline calculator; if you're ready to file now, see our Claim of Lien package. Not sure which deadline applies yet? Read our step-by-step filing guide and last-date-of-furnishing guide next.