Last Date of Furnishing in Georgia: Why This One Date Decides Your Lien
If you're planning to file a Georgia mechanics lien, one date matters more than any other: your last date of furnishing. Under O.C.G.A. § 44-14-361.1, a claim of lien must be filed within 90 days after you complete your work or last furnish materials, labor, or machinery to the project. Get that date wrong and the rest of the paperwork doesn't matter. Treat day 90 as a hard stop and plan to file well before it. Get it right, and you have a realistic picture of how much time is left.
Most contractors assume their last date of furnishing is obvious: whenever the crew packed up the truck for good. In practice, it is a date owners and general contractors often dispute. Owners and general contractors who don't want to pay have every incentive to say your real last date was weeks earlier than you think. If they can push it back far enough, your 90 days close before you ever record the lien.
What "Furnishing" Actually Means
The statute measures the 90 days from your completion of work or your last furnishing of materials or machinery. O.C.G.A. § 44-14-361.1 That rule doesn't refer to your invoice date, the owner's payment date, or the day the whole project finished, so don't calendar from any of those. Your last date of furnishing is about your work on that job, not the calendar of anyone else's.
The safest date to work from is the day you finished the main body of your contract work or made your last delivery of materials or machinery to the job. If you think a later date applies, have an attorney confirm it before you rely on it.
Your Last Date, Not the Project's Last Date
On any real job, there isn't one "last date of furnishing" for the whole project. There's one for every contractor, subcontractor, and supplier on it. Under O.C.G.A. § 44-14-361, lien rights extend to contractors, subcontractors, sub-subcontractors, material suppliers (though only suppliers who furnish to the owner, a contractor, or a subcontractor; a supplier to another supplier has no lien rights), laborers, certain registered design professionals, and equipment lessors. Each of you has your own contract, your own scope, and your own 90-day clock. The framing crew that finished in March and the trim carpenter still finishing in June are not on the same deadline, even on the same building. Track your own last date. Don't assume it lines up with anyone else's.
Punch List, Warranty, and Repair Visits: Don't Build Your Deadline on Them
Here's where disputes often start. A crew goes back to fix a squeaky door, touch up paint, honor a warranty call, or knock out a short punch list, then assumes that visit reset the 90-day clock. Don't count on it.
The statute counts 90 days from your completion of work or last furnishing. O.C.G.A. § 44-14-361.1 Whether a short return visit moves that date is a fact question an attorney has to evaluate, and it is the kind of date the other side will challenge. Don't plan your filing around it. You may find out it doesn't hold up only after the 90 days you thought you had are already gone.
The safer approach: count from the day you finished the main body of your contract work, not from a later return visit, and have an attorney confirm before you rely on any later date. If you genuinely aren't sure which date applies to your situation, that's a fact question a Georgia attorney should look at before you file, not after.
Documentation Habits That Protect Your Date
Because the last date of furnishing so often gets disputed, the contractors in the strongest position are the ones who can document their date. Build these habits into every job, starting now:
- Daily reports or job logs. A dated line noting what was done and by whom, kept as you go rather than reconstructed later.
- Delivery tickets. Signed by someone on site, showing what arrived and when.
- Signed timesheets or sign-in sheets. Dated records of who was on the property and on what day.
- Time-stamped photos. Material stacked on site, equipment in use, or work in progress, with the date visible or logged.
- Written communication. Emails or texts that confirm when final work was scheduled and completed.
None of this needs to be fancy. A phone camera and a habit of writing the date on delivery tickets will do more to protect your lien rights than any amount of paperwork assembled after the fact, once someone is already disputing your date.
What to Do If Your Last Date Is in Dispute
If you already suspect the owner or GC will argue about your last date of furnishing, don't wait to find out who's right. Gather your documentation now, while it's easy to find, and get a Georgia attorney to look at the facts before you file. If the date you relied on turns out to be wrong, the 90 days may already have run, and you may not get a second chance.
Frequently Asked Questions
What is the "last date of furnishing" under Georgia lien law?
Does warranty or punch-list work extend my deadline?
What if I only delivered materials and never performed labor?
Does my last invoice date count as my last date of furnishing?
If other trades are still working on the project, does that extend my deadline?
What happens if I miss the 90-day deadline?
Do I need proof of my last date of furnishing to file a lien?
Want a general estimate of your 90 days? Run the numbers with our Georgia lien deadline calculator, then email info@georgialiendesk.com to start a review. We check eligibility first and decline what we can't ethically file; if you qualify, our Claim of Lien package covers the filing. Contested litigation and bond claims are referred out or handled under a separate engagement. For the fuller deadline picture, see our guides on Georgia mechanics lien deadlines and how to file a mechanics lien in Georgia.