Affidavit of Nonpayment in Georgia

Here's a scenario that catches a lot of subcontractors and suppliers off guard: you sign a lien waiver so the GC can get draw funds released, the payment never actually shows up, and ninety days later the lien and bond rights that waiver covered are gone — not because you did anything wrong, but because you did nothing at all. The fix is a document called an Affidavit of Nonpayment, and in Georgia, since a 2021 change in the law, it is the only thing that stops that clock O.C.G.A. § 44-14-366. This guide walks through the 90-day rule, how the affidavit suspends it, how to serve it, and what an Affidavit of Payment does once you're finally paid.

The Story Behind the 90-Day Rule

Georgia requires lien waivers to follow specific statutory forms under O.C.G.A. § 44-14-366. Once you sign one of those forms, it becomes conclusively effective on whichever of these three things happens first:

Read that third bullet again. It doesn't say 90 days from your invoice date, or 90 days from your last day on the job. It says 90 days from the date you signed the waiver. If you sign a waiver, the payment you were promised doesn't come through, and you don't do anything about it, the waiver still becomes conclusively effective once the 90 days have run. Whatever lien or bond rights that waiver covered are gone. Not paused. Gone.

Deadlines are unforgiving. The dates on this page are general statutory rules — your deadline depends on facts like your last day of work, your tier, and recorded notices. If money is unpaid, start your review now, not the week the deadline lands.

How the Affidavit of Nonpayment Suspends It

An Affidavit of Nonpayment is a sworn statement, filed in the county where the property sits, that tells the record: the waiver was signed, but the money never arrived. Filed before the 90-day period runs out, it suspends the waiver's effect and preserves your lien and bond rights until you're actually paid O.C.G.A. § 44-14-366. File it after the 90-day period has expired, and there's nothing left for it to suspend. Don't plan around the last day — how your 90 days are counted is exactly what an attorney should confirm.

This is a genuinely narrow, hard deadline, and it's easy to miss precisely because nothing dramatic happens while it's running. No notice arrives telling you time is short. No court sends a reminder. The only warning is the date you signed the waiver, on a form you may have filed away without a second thought.

The rule changed in 2021 — and older articles online may still describe the old one. Before January 1, 2021, the window was 60 days, and filing a Claim of Lien was itself enough to stop a waiver from converting. Senate Bill 315 changed both of those things. Since that change, the window is 90 days, and filing a lien no longer stops the clock at all — only a timely Affidavit of Nonpayment does. Older articles that still describe a 60-day rule, or say a lien filing protects you, are describing the pre-2021 law.

Serving the Affidavit: the 7-Day Rule

Filing isn't the last step. Under O.C.G.A. § 44-14-366, a copy of the Affidavit of Nonpayment must be sent within 7 days of filing. The safe practice is to send it to the owner and, where a Notice of Commencement was filed for the project, to the contractor as well. Send it by registered or certified mail, or statutory overnight delivery, and keep proof that it went out and arrived. Sending that copy is a statutory requirement, not a courtesy — treat the 7-day mailing as part of the filing itself.

What Happens Once You're Actually Paid: the Affidavit of Payment

An Affidavit of Nonpayment isn't meant to sit on the record forever. Once the debt is fully paid, an Affidavit of Payment can be filed to void the earlier Affidavit of Nonpayment O.C.G.A. § 44-14-366, cleaning up the county's records to reflect that the matter is closed. It's the bookend to the process: nonpayment gets you the affidavit that protects your rights, payment gets you the affidavit that voids it.

Why the Timing Is the Whole Fight

Almost everything about this process comes down to dates: the date you signed the waiver, the date the 90-day period actually ends, and the 7 days after filing in which a copy has to be sent O.C.G.A. § 44-14-366. None of those dates are visible on a calendar unless someone calculates them from your specific waiver and your specific project. That calculation, and the eligibility review behind it, is exactly what determines whether there's still time to act or whether the window already closed. Georgia Lien Desk reviews eligibility first and declines what we can't ethically file; contested litigation and bond claims are referred out or handled under a separate engagement. Our current scope is private commercial Georgia projects with claims roughly $5,000 to $100,000, for contractors, first-tier subcontractors, suppliers (including suppliers to subcontractors), and equipment rental companies.

Frequently Asked Questions

What is an Affidavit of Nonpayment in Georgia?

It's a sworn statement filed in the county where the property is located, before the 90-day period after signing a lien waiver expires, that suspends the waiver's effect and preserves your lien and bond rights until payment O.C.G.A. § 44-14-366.

Does filing a Claim of Lien stop the 90-day waiver clock?

No, not anymore. Since SB 315 took effect January 1, 2021, filing a Claim of Lien is no longer sufficient to stop the 90-day conversion of a signed waiver. Only a timely Affidavit of Nonpayment stops it O.C.G.A. § 44-14-366. Older articles online that say a lien filing works, or that the window is 60 days, describe the pre-2021 rule.

What happens if I sign a lien waiver and never get paid?

A signed waiver becomes conclusively effective on the earliest of actual receipt of payment, written acknowledgment of payment, or 90 days after the date the waiver was signed O.C.G.A. § 44-14-366. If neither of the first two happens and 90 days pass with no Affidavit of Nonpayment on file, the waiver takes effect and the lien and bond rights it covers are gone.

Do I have to send a copy of the Affidavit of Nonpayment to anyone?

Yes. A copy must be sent within 7 days of filing, by registered or certified mail or statutory overnight delivery O.C.G.A. § 44-14-366. The safe practice is to send it to the owner and, where a Notice of Commencement was filed, to the contractor as well.

What is an Affidavit of Payment?

It's the counterpart filing used after full payment is received, which can void a previously filed Affidavit of Nonpayment now that the debt behind it has been satisfied O.C.G.A. § 44-14-366.

How much time do I have to file an Affidavit of Nonpayment?

It must be filed before the 90-day period following the date you signed the lien waiver expires O.C.G.A. § 44-14-366. Because the 90 days runs from the waiver's signature date, not your invoice or last day of work, the deadline should be calculated for your specific waiver rather than estimated.

Georgia Lien Desk's Affidavit of Nonpayment package covers attorney preparation, filing, and service of your affidavit for a flat fee. Whether there is still time on your specific waiver is determined in the attorney review, so start as early as you can. If you're not sure whether your 90 days have already run, get a general estimate from the lien deadline calculator, and read our guide to Georgia lien waivers to understand why the waiver you signed matters as much as the payment you didn't get. Our guide on Georgia mechanics lien deadlines covers how this fits with your other filing deadlines.

Unpaid on a Georgia project? Don't let the clock run out.

Tell us about your project. A Georgia lawyer reviews your lien rights and, if you qualify, prepares and files the paperwork — for a flat fee stated before you pay.

Start My Review