What Happens After a Lien Is Filed in Georgia
Filing is only the first step. What happens after a lien is filed in Georgia matters just as much as getting it recorded on time, because a claim of lien creates deadlines of its own and it invites the owner or contractor to respond. Here's the sober version of what comes next, with no promises about how fast, or whether, anyone pays.
Step One: Recording and Service
Your Claim of Lien is filed with the clerk of superior court in the county where the property sits. That part is mechanical. What isn't optional is service: under O.C.G.A. § 44-14-361.1, a true and accurate copy must go out no later than 2 business days after filing, by registered or certified mail or statutory overnight delivery, to the owner (or, if the owner's address can't be found, to the contractor as the owner's agent; if the owner is an entity on file with the Georgia Secretary of State, service to that entity's or its registered agent's address satisfies the rule). If a Notice of Commencement was filed for the project, a copy must also go to the contractor at the address listed on that notice. Service is a statutory requirement, not a courtesy.
What the Lien Actually Does
A recorded lien secures your debt against the property. It does not force anyone to pay you, and it doesn't move money on its own. What it does is create a real problem for the owner and, often, the general contractor: a lien on record can complicate a sale, a refinance, or a construction draw, because title companies and lenders don't like clouded title. That can create pressure, but it's indirect. Some owners move quickly once a lien shows up. Others don't move at all until they're forced to. We won't tell you which one you're dealing with: only that the lien's pressure comes from the property's title, not from the document itself.
The 395-Day Warning on the Face of Your Lien
Georgia requires every claim of lien filed after March 31, 2009 to carry a 12-point bold warning on its face, under O.C.G.A. § 44-14-367: that the lien "expires and is void 395 days from the date of filing of the claim of lien if no notice of commencement of lien action is filed in that time period." Don't read that as 395 days to act. The working deadlines come earlier: a lien action must be commenced within 365 days from the date the claim was filed for record, and the Notice of Commencement of Lien Action is due within 30 days after you commence that action, not 30 days after day 365. O.C.G.A. § 44-14-361.1
The Real Clock: 365 Days to Sue, 30 Days to File the Follow-Up Notice
Under O.C.G.A. § 44-14-361.1, you must commence a lien action within 365 days from the date the claim of lien was filed for record. Then, within 30 days after commencing that action, you must file a Notice of Commencement of Lien Action with the clerk of superior court in the county where the lien was filed. Both steps are statutory requirements. Have an attorney calendar both. This filing is separate from the project's own Notice of Commencement, which is a different document filed by the owner or contractor for the project itself. Don't confuse the two just because they share part of a name.
How Owners and Contractors Respond
A recorded lien doesn't sit unanswered forever. Owners and contractors have real options, and it's worth knowing them so nothing catches you off guard:
- Pay or negotiate. Some owners and contractors choose to resolve the claim once a recorded lien is in the way of a closing or a draw. Nothing requires them to, and no filing guarantees payment.
- File a Notice of Contest of Lien. This is a formal move that puts you on a much shorter clock. O.C.G.A. § 44-14-368 See our guide to a Notice of Contest of Lien in Georgia for what it does to your deadline.
- Post a bond. Owners can substitute a bond for the property; the lien then attaches to the bond. O.C.G.A. § 44-14-364
None of these responses are personal. They're standard moves available to any owner or contractor facing a recorded lien, and seeing one doesn't mean your lien was invalid or improperly filed.
What You Should Be Doing During This Window
Once your lien is filed and served, the clock doesn't pause. Calendar your 365-day deadline the same day you file. Keep records of every communication with the owner or contractor. If you get a Notice of Contest, don't wait to see what happens next. That document shortens your timeline dramatically. And if 365 days is approaching with no resolution, talk to a Georgia attorney about actually enforcing the lien before it lapses.
Frequently Asked Questions
How long is my lien enforceable after I file it?
Do I need to send notice after recording my lien?
Can the owner just refuse to pay and ignore the lien?
What if the owner says the general contractor was already paid in full?
What is the 395-day warning printed on my lien?
What happens to the lien once I get paid?
I'm the owner and a lien was just filed against my property. Can Georgia Lien Desk help?
If your 365-day enforcement clock is running, don't let it lapse quietly. If you haven't filed yet, we review eligibility first and decline what we can't ethically file; our Claim of Lien package includes a deadline note for your file, and we do not monitor that deadline after the engagement ends. Filing the lien action itself is contested litigation, which we refer out or handle under a separate engagement. Run your dates through the lien deadline calculator for a general estimate, and if a Notice of Contest shows up, read our guide on what a Notice of Contest of Lien means for you right away.